on 2025 Jan 31 7:57 AM
Hello,
I am currently facing the issue that inbound deliveries for a production order are not getting created automatically after confirming the production order. I identified that the issue is based on the fact that no vendor can be determined for that delivery.
Would someone be so kind to link me the IMG-path for determining the supplier for inbound deliveries from production?
Thanks and best regards,
Jonas
Request clarification before answering.
I would suggest you to check t001w table, if supplier assigned to the plant