Subcontracting Purchase Requistion (SNP) becomes Standard Purchase Requisition (MM)

Former Member
0 Likes
614

Dears,

-T-Lane exists wrt a purchase info-record of form subcontracting that was brought over from ECC.

-A purchase requisition created in SNP understood that t-lane and faithfully determined the source of supply.

-This purchase requisition at first refused to go to ECC citing missing Purchase organization (Enter Purchase Org)

-But I deleted these queues failing to understand what the H does it mean when all concerned master data animals like Purchase info record and T-Lane and Ext Proc relation have a unique Purchase org in both source and target systems

- I than ran CCR report and managed to whip these purchase requisitions to ECC (ideally it should create the same missing purchase org queues again)

- These purchase requisitions in ECC now have a) An entirely different inforecord b) A document type NB which is standard purchase requisition and NOT a subcontracting purchase requisition.

- There is no special procurement key in material master

- There are no BADIs and Z animals in anywhere

Question:

Why is ECC determining the source again when APO has already done it?

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

Are there multiple source of supply available in APO or ECC?

Please make sure T lane and Ext. Proc. Relationships created as subcontracting as source as Info record.

Also check item category in Purchase requisition as L for subcontracting.

Check if you have any source list used for this material in ECC.

Best Regards,

R.Brahmankar

Former Member
0 Likes

Rupesh,


You are THE MASTER. I bow down. I wish I had the good fortune of becoming your protege in my mid-20's. I am now 45 and practically useless.

Thanks

Amit

Answers (1)

Answers (1)

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

Procurement Type F-30 in ECC will help here for source determination

Please refer SAP consulting not 369921 - Subcontracting and SNP

No subcontracting purchase requisitions can be created with the SNP heuristic. The only option you currently have to create subcontracting purchase requisitions in the APO is through a PPDS planning, CTM planning

The SNP heuristic and SNP optimizer cannot create any subcontracting purchase requisitions.

Best Regards,

R.Brahmankar