on ‎2019 Aug 30 5:40 AM
Dears,
-T-Lane exists wrt a purchase info-record of form subcontracting that was brought over from ECC.
-A purchase requisition created in SNP understood that t-lane and faithfully determined the source of supply.
-This purchase requisition at first refused to go to ECC citing missing Purchase organization (Enter Purchase Org)
-But I deleted these queues failing to understand what the H does it mean when all concerned master data animals like Purchase info record and T-Lane and Ext Proc relation have a unique Purchase org in both source and target systems
- I than ran CCR report and managed to whip these purchase requisitions to ECC (ideally it should create the same missing purchase org queues again)
- These purchase requisitions in ECC now have a) An entirely different inforecord b) A document type NB which is standard purchase requisition and NOT a subcontracting purchase requisition.
- There is no special procurement key in material master
- There are no BADIs and Z animals in anywhere
Question:
Why is ECC determining the source again when APO has already done it?
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
Hello,
Are there multiple source of supply available in APO or ECC?
Please make sure T lane and Ext. Proc. Relationships created as subcontracting as source as Info record.

Also check item category in Purchase requisition as L for subcontracting.
Check if you have any source list used for this material in ECC.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Procurement Type F-30 in ECC will help here for source determination
Please refer SAP consulting not 369921 - Subcontracting and SNP
No subcontracting purchase requisitions can be created with the SNP heuristic. The only option you currently have to create subcontracting purchase requisitions in the APO is through a PPDS planning, CTM planning
The SNP heuristic and SNP optimizer cannot create any subcontracting purchase requisitions.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 14 | |
| 9 | |
| 8 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.