Subcontracting considering in-house production capacity as constraint in PP/DS

acoguist
Explorer
0 Likes
326

Hi,

Now I have a situation like below;

We have a demand as 100 pc for a particuler week, and only 70 pc can be produced considering the in-house production capacity. Here what I expect is that system automatically creates both planned order for 70 pc as in-house production and purchase requisition for 30 pc as subcontracting.

Is that possible in PP/DS?

I know SNP CTM can do this, but now we have only PP/DS.

Thank you in advance. NS

Accepted Solutions (0)

Answers (2)

Answers (2)

acoguist
Explorer
0 Likes

Hello,

Thank you very much for your comment.

Now I got it.

Best regards,

Sugiyama

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

You can product in In-bound Quota arrangements in PPDS to determine the Source of Supply selection as inhouse as well as external.

Please refer useful wiki link on it,

Scenario - Planning with Quota Arrangements in PPDS

However it is not possible on the basis of capacity, you can do that fix ration like 30 In-house and 30 subcontracting.

or use SAP_REM_001 heuristic, which distributes the orders among the different sources.

Best Regards,

R.Brahmanakr