on 2023 Nov 30 2:42 PM
Looking for some help. How are need dates calculated for the lower level material that is to be shipped to a vendor when the material as a lead time off set assigned.
Generally with no offset the need date is calculated based on the delivery date minus the product lead time. But if a part has an offset assigned how is the need date calculated?
Thanks
Request clarification before answering.
I use Lead Time Offset for my subcontracting purchase orders so that the material is required to be available before the date the purchase order is shipped to the vendor.
I have -7 in the BOM (CS02) for each component. This ensures the requirement date of the component is 7 working days (per the plant factory calendar) prior to the Release Date which is when the material is expected to be shipped to our vendor.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
6 | |
4 | |
3 | |
2 | |
2 | |
2 | |
2 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.