Sub assembly planing within next higher assembly

Former Member
0 Kudos
227

I have an assembly A and sub assembly B that need remanufactured.

Assembly A Route – Disassembly 2 days, Reassembly 2 days, Test 2 days.

Sub Assembly B Route – Disassembly 4 days, Repair 5 days, Reassembly 4 days.

Sub Assembly B is allocated to the reassembly operation of assembly A. Sub assembly B cannot start until after disassembly of assembly A is complete. Is there any way to plan this so the planned order for sub assembly B does not start before Assembly A is disassembled?