on 2023 Dec 04 8:26 AM
When a planning run takes place in PPDS and orders (PO and Preqs) are created/changed in a planning run. If you do not want to transfer changes from APO to ECC without deactivating CIF IM. How can we achieve it?
Request clarification before answering.
1. Option would to run PP/DS in a planning version != active planning version.
2. Option would to filter out the changes for the specific plant, planner etc. in the CIF and delete them. Set the CIF transfer to collect changes /SAPAPO/C4 (make sure to also select background user & the user for which you don't want to transfert results) then in SAPAPO/C5 delete the objects (only high level - think about the details like including background user etc.)
With this you have the option do only transfer results for select plants, material etc. etc. or no at all - but you don't have to turn off this CIF.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
5 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.