We have ALCM (Asset Life cycle management) project running at the moment and go live will be 1st of September 2020. Some maintenance plans are already running like 3M, 6M and 12M in Single cycle.
We are moving to Strategy Base plan.
My question:- is there any way,we can set start data of plan at operation level.
If we will give start data as 15.09.2020, the 3M will start from 15.12.2020, But others like 6M and 12M will start from 15.03.2021 and 15.09.2021 respectively
In AS IS situation, we have all 3M,6M and 12M is schedule in Dec 2020
in TO BE, We want to schedule it in such a way that 6M and 12M also starts in Dec 2020.
I cannot see any Off set field for operation.
Your early response will be much appriciated.
Thanks
Sudip
Request clarification before answering.
If i understand your request, the easiest way to accomplish this is to create strategy based task lists that have the strategy with packages for the 3M, 6M. 12M, etc time frames. You can then assign each operation in the task list to the requisite package(s) as needed, Your strategy can also have a hierarchy if needed so that when the 6M operation is called, the 3M is not included, depending on the needs. You can then include the task list in the maintenance plan and start the plan in cycle to align to next applicable operations to be performed. This is a simple explanation that has several pieces that need to be set-up and though through carefully to enable the correct maintenance activities. Hope this helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 14 | |
| 9 | |
| 8 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.