2021 Mar 12 12:54 PM - edited 2024 Feb 04 12:26 AM
Dear experts,
I have a question regarding the rough cut capacity planning for product group when using flexible planning (MC93/MC94).
I created a Z
info-structure using Product group/material and plant as characteristics and I created planning hierarchy multilevel with materials as last level: (example of one branch)
PG1/plant
PG1-1 /plant
PG1-1-1/plant PG1-1-2/plant
MAT1/MAT2...(plant of course)
Everything is working fine except the capacity planning.
In MC93/94 When I want to check capacity via View-> Capa situation -> RCP -> Show this option is grayed out when I'm planning Product groups (PG1-1-1 for example) ! I have already created RCC profile and OPU4 is setup correctly. The characteristic production is also assigned to info structure for capacity (See attached)

When I do the same for material (MAT1 for example) it is working correctly, but not for higher levels 'product groups:

I also checked by planning this material group via standard sop and it is also working fine, but in my scenario I will not be using standard SOP.
I've checked almost all the questions around this topic here, but nothing that answer this issue.
We are on EHP3.
Thanks in advance.
Request clarification before answering.
| User | Count |
|---|---|
| 12 | |
| 9 | |
| 8 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.