on 2017 Apr 25 8:18 AM
Hi Experts,
We run the SOP operator(S&OP Heuristic W2M), but faced two messages as follow (Type is error & information).
1. Message Type 'E',No.729, 'Invalid planning unit data for planning unit SPA; invalid planning unit key (Error Code 6)'
2. Message Type 'I',No.1009,'Invalid sourcing for location 2010, product WHEEW001 and time period ID 52957: Sum over quotas is 2.000000 (outside of allowed deviation)'
We success to run the SOP operator one week ago,and do not change the master data, key figure data since we successed.
But the error is occurred in this week.
Does anyone know how to solve this issue?
I confirm the note 2456479, but can not resolve this issue.
2456479 - IBP: invalid planning unit key (Error Code 6)
Best Regards,
Yuji
Request clarification before answering.
Hello Gabriel,
Thank you for your reply.
I set the Planning unit configuration (field name is PLUNITID).
So, this error is resolved.
Thanks and best regards,
Yuji
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
6 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.