SNP PDS without Resource (and Activity)

former_member568621
Participant
0 Kudos
1,622

Experts,

SNP PDS (curto_simu) does not have resources for the activities / operations CIFd from ECC.

  • Resource in CIFd and assigned to active model and version
  • Resource / work center is valid in ECC
  • PDS (SNP production detailed planning) is valid
  • Operation dates are valid and is CIFd with PDS integration model
  • Production version is not locked
  • All master recipe data exists
  • Resource is relevant for APO with finite capacity checked.
  • No queues
  • Delta and initial transfer done multiple times INCL. deleting orders, resources, PDS in APO all over again.
  • Did CURTO_CREATE and PDS_MAINT too in ECC.
  • This happens with ALL production versions of SOME material plants.

What could be the possible reasons?

Thanks

Amit

Accepted Solutions (1)

Accepted Solutions (1)

Abhishek_Kunchala
Active Participant
0 Kudos

Hi Amit,

Does the resource have setup/processing formula maintained in Scheduling tab of Work Center in ECC? What is the UoM for capacity in Work Center and UoM in Recipe?

Answers (6)

Answers (6)

former_member568621
Participant
0 Kudos

Abhishek,

Yours was the correct root cause. IF the scheduling formula for activity time is NOT maintained or is NOT determinable from resource capacity header, Activity and Resource are NOT CIFd to APO. There is no error or warning message on this count in CIF or APO. So many dozen things to check post facto.

You may like to add to the check list above for future bhaktatmas like me. Such a check list wont be available on help.com, service.com, notes combined. Prerequisite checks to CIF PDS to APO. That said PP is really well documented vis a vis APO where I have to guess unlabelled animals all the time.

Thanks

Amit

former_member568621
Participant
0 Kudos

Thanks Rupesh, done multiple times over.. no effect

rupesh_brahmankar
Active Contributor
0 Kudos

Hello,

Please share the screen shot of master recipe of phase and operation screen.

Also delete the PDS in APO system /SAPAPO/CULL_RTO_DEL - Delete Production Data Structure then again CIF it from ECC system.

Best Regards,

R.Brahmankar

former_member568621
Participant
0 Kudos

Thanks Vanam


We do not use routing. Our PDS is based on Master Recipe only. I note all operations and corr activity times are maintained.

rupesh_brahmankar
Active Contributor
0 Kudos

Hello,

Please reactive CIF integration model for resource and PDS CFM1/CFM2 then also execute RIMODINI for these IMs and check it again.

Best Regards,

R.Brahmankar

lingaiahvanam
Active Contributor
0 Kudos

Hi,

Check the following setting once again or create new product structure and CIF to APO.

During PDS transfer there are different checks regarding the validity of the operation. If one of these checks fails (see solution section) the operation will be filtered out.

This is visible in transaction /SAPAPO/CURTO_SIMU where the tabs for operations, activities and activity relationships are missing or in transaction /SAPAPO/RRP3 when displaying an order.

1. A scheduling-relevant control key must be assigned to the operation. This means the control key has to have the flag "scheduling" set.

Example routing in transaction CA03:

ca03.png

2. A work center relevant for planning must be assigned to the operation. Relevant for planning means that for the target system the work center is contained in an active integration model for work centers (ERP to SCM APO) or marked as advanced planning relevant (PPDSonERP or Embedded PPDS).

Transaction CFM1 - Creation of Integration models for work centers:

cr03.png

3. The operation must have a duration. That means that in the work center a formula must be assigned to the capacity category relevant for scheduling and the times maintained in the routing/recipe have to be greater than zero. At the end the system must be able to calculate with the times and the formula an operation duration greater than zero.

Example routing with operation times in transaction CA03:

ca03-1.png

Example work center from the routing in transaction CR03:

cr03-1.png

4. The operation has to be valid regarding the date. This means when a PDS gets transferred the filter data is per default set to today. Any operation whose valid-to date is before today gets filtered out because past data will not be considered as planning relevant any longer.

  1. Additionally when transferring SNP PDS operations with a valid-from date in the future will be filtered as well (please read SAP note 1138338 for more information on this and how it can be influenced).

Example routing in transaction CA03 with validities of operations:

ca03-2.png

The above described behavior is current standard. If there is a need to influence this the BAdI CUSLNTRTO_ADDIN can be used to place some own coding which changes the logic.

https://launchpad.support.sap.com/#/notes/2749682

Best Regards,

Lingaiah

former_member568621
Participant
0 Kudos

Thanks Vanam


Production Versions are valid for another 10 millenniums

lingaiahvanam
Active Contributor
0 Kudos

Hi,

Check the production version validity dates once again.

Best Regards,

Lingaiah