on 2014 Nov 27 2:39 PM
Hi All,
i faced with error in SNP optimizer, it shows me a message "Duration of PPM/PDS &1 is too long".
I have planning book with daily buckets, SNP PDS has duration for 1 day.
If plan in planning book with week buckets all is ok.
Any ideas how to solve this issue.
i use resource with standard 24x7 hours with active "Cross-period activity" and "Sequence-Dependent lot size".
Request clarification before answering.
Hi Alexander,
Did you check the work center horizon? Must to be equal with SNP planning book horizon!
Thanks.
Regards, Marius
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Alexander,
This is about the PDS uses a resource for sequence-dependent lot-size planning, and the gross duration exceeds the length of period.
Please check the time bucket profile used in your SNP Optimizer, and use a time bucket profile with longer periods, so that the PDS can be scheduled without being cross-period.
Hope it helps.
Best regards
Mandy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 8 | |
| 6 | |
| 3 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.