on ‎2015 Jul 07 4:06 PM
Hi,
Can anybody please provide me complete scenario for RO (For demand)
I am very new to SNC. So please provide the end to end scenario details and also required pre-requisite like master data.
Regards,
Manikandan G
Request clarification before answering.
Hi Manikandan
please go through the below link. Thereafter you can come with specific questions.
Replenishment Order Collaboration - SAP Library
If this already answers your question do follow
http://scn.sap.com/community/support/blog/2013/04/03/how-to-close-a-discussion-and-why
regards
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Helo Manikandan,
I had Implemented RO process recently for our client Successfully:
There are few Configuration which you need to Take care:
1) MRP Type to be used as X0 (Standard) in Material Master MRP View
2) Create a Contract with CONF Control Key having AB and LA both
3) Maintain Vendor Master Settings: Order Entry BY Vendor Settings Enabled- Purchasing Data
4) Maintain WVM7 (T Code in ECC) Settings for RO Process
5) Master data Settings in SNC for RO Process, define Number range attributes for PO and SO (Master Data <> Number Ranges)
6) Maintain Number Range Attributes for PO and SO (Master Data <> Number Ranges)
7) Maintain Number Ranges for RO in SPRO, for internal Number Generation (SPRO <> RO <> Determine Num Ranges for RO
😎 CIF Material, Vendor, Contract <> Check T Lane to have Contract reference
9) PROACT Your Demand to SNC
10) Create RO from SMI Overview against Planned receipts
11) Create ASN Against RO from RO Overview
12) Maintain XI to ECC settings for VGON_Out Mapped to ORDRSP IDOC Type, so RO from SNC can go to ECC and Create PO.
Hope this Information is helpful.. reward if its working for you..
Regards,
Guru
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Manikandan,
I guess you are looking for the SNC Customer Collaboration process. Is that correct?
Standard SCM SNC has mainly used for 2 scenarios:
1- Supplier Collaboration
2- Customer Collaboration
If you want to learn in details the you should be aware that Replenishment can run for both scenarios.
You can refer the below SAP Help link:
This link provides information for both VMI & SMI scenarios.
In both areas, solutions requirements are changing for master data, planning and interfaces. You will be sending a lot time in below customizing areas:
Kindly feel free to reach if you have further questions.
Regards,
Selim
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 15 | |
| 9 | |
| 8 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.