Hello Experts,
I have an error scenario as given below:
1) Packaging material line item was manually added in EWM ODO.
2) During goods issue, the inbound queue in ECC failed to create the packaging material line item in ECC because of error 'Essential transfer parameters are missing in record'.
I think one way of resolving this queue error would be to debug the LUW and insert the missing parameters. Alternatively, is it possible to edit the queue container in SMQ2 and insert/change the necessary parameters?
Thanks.
Request clarification before answering.
Hi Ruturaj,
basically this should work without having to do anything with the qRFC.
Please check if in the /SCWM/PRDO on the PPF tab a PPF action was scheduled to transfer the new pack item to the ECC system. This should have happened when you create the new pack item. So it first has to be checked if the new item was transferred to ECC upfront the GI. Check if the PPF action exists and/or if it was processed or failed.
Debugging and changing a queue entry is usually no good idea. Why do you want to do this? I hope/assume that you are in a test system where you can check the configuration and test until the process works fine.
Maybe related info which could also be of interest for you:
https://help.sap.com/viewer/3d97bec9bf1649099384bb8167df3cf2/9.5.0.1/en-US/379b1052bfd79933e10000000... (this is not exactly the same as you want to do this manually but maybe it still can be of interest)
Best regards
Markus
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 3 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.