Hi experts,

I cannot find in SAP 7.0 where in ECC I can complete the set up key and the setup group, and also set the Set up activity flag in the setup activity of the recipe. These parameters are visualized in /SAPAPO/CURTO_SIMU but they cannot be completed in APO, I couldnt find in ECC where to enter these parameters.

Please help!

View Entire Topic
rupesh_brahmankar
Active Contributor

Hello,

•Flag "SetupActivity" must be set in PDS, Activities tab

•Setup matrix must be maintained for the resource (/SAPAPO/RES01)

•Resource should be set as finite scheduling Resource must to be a single/single-mixed resource. Meaning that for the capacity in the Work Center on ECC side the "Number of Individual Capacities" must NOT be bigger than 1 and that the flag "Can be used by several operations" must NOT be set.

Refer SAP KBA 2514471 - Scheduling is not considering Setup Matrix

You also need to maintain the following activities

/SAPAPO/CDPSC6 - Maintain Setup Groups

/SAPAPO/CDPSC7 - Maintain Setup Matrix

Please refer,

Determining Setup Time for Sequence-Dependent Setup Activities

Best Regards,

R.Brahmankar

Former Member
0 Likes

Sorry but my question was: In which transaction, specificately, I have to complete these two points?:

  • You defined the necessary setup status for processing the operation by assigning a setup group or a setup key to the operation.
  • You defined a setup activity for the operation.

I cannot find it in the recipe (ECC- trx: c202) and in APO (TRX: CURTO_SIMU) I cannot edit.