on 2019 Apr 24 9:34 AM
What are the steps to configure a material in ECC and APO as MTO?
The steps you take are: Configure the material in the MRP3 view
Create a Sales order
Run the heuristics in APO and generate the planned order When wanting to generate the Process order from the planned order, in the transaction / sapapo / rrp3 the system generates nothing.
in MD04 throws the error: You can not make an assignment to make-to-order stock Message no. CO684
Request clarification before answering.
Hi Brahmankar,
I have configured only one material. In MM02 -> MRP3 -> Strategy group = 20 In MM02 -> Sales organization 2 -> Item category group = 001 Run Heuristic in APO, create Purchese order in production plant Run Heuristic in Production plant and create planned order. I can create process order in APO -> RRP3 I can create process order in MD04
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Does it work with ECC? May be you can change the MRP type to PD and run MRP with MD50 and check it.
Or by using Transaction CO08, can you create a production order with reference to a sales order?
Best Regards,
R,Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Does this issue with particular material or all MTO materials?
What is planning strategy are you using and what is the requirement class in sales order?
In OKKP Controlling Area is active for Sale order under Activate components/control indicators
Also refer SAP consulting note 459734 - How does the order account assignment work?
Best Regards,
R.Brahmankar