on ‎2019 Aug 07 12:37 PM
Hello,
I have a question about the TS Supply Planning.
I have a production with 3 production ressoruce. Let me called as
PRODRES1
PRODRES2
PRODRES3
our finish product will produced with all 3 ressoruce. Now I want, that in the TS Supply Planning the sequence of the ressoruce will be consider. That means, first PRODRES1, ...,PRODRES3
is this possible and how can I manage this in IBP ?
Regards
Oliver
Request clarification before answering.
Hello Oliver,
You could try to create 3 "versions" of the FG, for example:
And then, using a PLEADTIME = 0, the BOM could be as follows:
PRODUCT1_V1 used as Component for PRODUCT1_V2; and PRODUCT1_V2 is used as Component for PRODUCT1_V3. The real PLEADTIME could be used only for PRODUCT1_V3.
Best regards,
Matheus
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 14 | |
| 9 | |
| 8 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.