Sequence dependent set up activity deos not have mode

aravind_sankar
Participant
1,170

Dear Experts,

Once after conversion indicator set in RRP3/4, these planned orders gets converted to Process order in ECC but while cifing it back, getting stucked in Queue with the error - Sequence Dependent set up activity does not have mode.

Can anyone plz help to understand what could be the issue either it is in APO or in ECC.

Thanks,

Accepted Solutions (1)

Accepted Solutions (1)

tiago_furlanetto
Product and Topic Expert
Product and Topic Expert

Hi ASM S,

When you first create the planned order, does it contain a sequence-dependent setup activity in APO? If not, do you expect one to exist?

This issue can be caused if the validity start of the PDS is earlier than the validity start of the sequence-dependent setup activity. In this case, when you create the PlOrd in APO it may not contain the setup activity. When you convert it to Process Order it is sent to ECC and the setup phase is added to the order over there and CIFed to APO. In APO, no mode exists for the activity, thus the error is raised.

Regards,
Tiago

Answers (1)

Answers (1)

former_member182332
Participant

Hi ASM,

Kindly check the recommendation from the note 2184011. make sure that all the points from the notes are valid in your case and this should help solve your issue

Thanks

Gomathi