Hello, When I create a debit memo and I Immediately refresh process receivables, I see my debit memo on process receivables, I was thinking we should run T code FDM_COLL_SEND01 for that, Can you please confirm? or Is Process receivables always real time from FI to FSCM?
Hi mukeshreddy,
The data in collections management is never real-time data. It is essentially a snapshot that is transferred from FI-AR to Collections Management by a program FDM_COLL_SEND_ITEMS.
SAP recommends to run the program FDM_COLL_SEND_ITEMS (t-code FDM_COLL_SEND01) with the option "Periodic data transfer" on a daily basis in a background job. The program will update the data in Collections Management based on the latest FI-AR transactions. The data in Collections Management will then be used to generate worklists / assign them to collection specialists. To automate the generation/update of worklists another background job should be scheduled for a program UDM_GEN_WORKLIST (t-code UDM_GENWL).
Regards,
Bohdan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
6 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.