Hello Folks,

I'm using PM.

I have a work order which i send for picking.
Some of the material is not available in the warehouse.

currently i need to removed the material out of the work order, write myself a note, and later, when the work order is partially performed, i need to add the material back into the work order.

the reason why i am doing this is, because the warehouse would have a picking information about the material which is not available.

Question:
Is there a way, that i can send the work order for picking, and pause that particular material, which i know, which is not availabe?

moshenaveh
Community Manager
Community Manager
0 Kudos

planning_noob

Welcome to the SAP Community. Thank you for visiting us to get answers to your questions.

Since you're asking a question here for the first time, I'd like to offer some friendly advice on how to get the most out of your community membership and experience.

First, please see https://community.sap.com/resources/questions-and-answers, as this resource page provides tips for preparing questions that draw responses from our members. Second, feel free to take our Q&A tutorial at https://developers.sap.com/tutorials/community-qa.html, as that will help you when submitting questions to the community.

I also recommend that you include a profile picture. By personalizing your profile, you encourage readers to respond: https://developers.sap.com/tutorials/community-profile.html.

Now for some specific suggestions on how you might improve your question:

* Outline what steps you took to find answers (and why they weren't helpful) -- so members don't make suggestions that you've already tried.

* Share screenshots of what you've seen/done (if possible), as images always helps our members better understand your problem.

Should you wish, you can revise your question by selecting Actions, then Edit.

The more details you provide (in questions tagged correctly), the more likely it is that members will be able to respond.

I hope you find this advice useful, and we're happy to have you as part of SAP Community!

Accepted Solutions (0)

Answers (1)

Answers (1)

nikhilnegi1
Participant
0 Kudos

Hi Fred,

If the material is not available in the warehpouse, then in EWM the warehousetask creation will get failed, but you can still see the overview what all items that are supposed to be planned or part of outbounds.

Regards,