Hello Guru's,

I am working on a SNP implementation for one of our division which is heavy on SD scheduling agreements but we do not want to use extensive functionalities of APO Scheduling Agreements, we want to manage Scheduling Agreements only in ECC, and use SA Schedule lines as input for SNP. I have CIF'ed all scheduling agreements into APO and see them in the report /SAPAPO/RRP3 but I am not seeing them in the interactive planning.

Thank you

Srikanth

Accepted Solutions (1)

Accepted Solutions (1)

former_member200970
Participant
0 Likes

Hi, Srikanth,

Can You please find was there any strategy profile maintained for interactive planning in global parameters and default values. Let us know did the clue helped you.

Best Regards

Arvind Pabba