on ‎2020 Apr 23 11:34 AM
Hello Experts,
We have a scenario where client wants to consider STO quantities during ATP check doe sales order. We have configured it in scope of check. In MD04 and CO09 i can see system considers STO and shipping notification for cumulative ATP quantity. But what client wants is different. Client wants that if we are receiving STO in future then system should create additional schedule line in sales order based on the STO dates. But at the moment we only get single schedule line which confirms everything. Is there a way in which system creates different schedule lines based on STO/PO dated in sales order.
I tried changing configuration by updating flag as A or X for planned purchase orders but it doesn't work. Could you please suggest how to get ifferent schedule lines based on STO/PO dated in sales order.
Thanks
SK
Request clarification before answering.
Hi Brahmankar,
We are using AATP as we are implementing S4 HANA 1809. Requirement is to considers future STOs and shipping notification. So ideally if on hand stock is 1000 and STO is for 150 in future then we should have 2 schedule line. One with on had stock and 2nd one for future receipts.
Also we are not considering RLT as we only want to consider on hand stock and planned future supply. See the attached screen shot of scope of check.

You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Are you using gATP or ATP?
Are you considering the RLT for confirmation?
Does STO confirmation is in future?
Please share your scope of check setting along with MD04/CO09 screen shot.
Best REgards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 12 | |
| 8 | |
| 4 | |
| 3 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.