SAP TM Resource capacity for products

0 Likes
779

Hello Experts,

I have a FUBR with splitting all the products by 1 ton. I have a resource with 10 ton capacity So, the scenario is that Product1 can be loaded to this resource with 10 tons, but Product2 can be loaded only with 8 tons (bc volume is higher, it doesn't matter). If I left the resource capacity with 10 tons it will be planned with Product2 with Full load = 10 tons. How can I fix it?

Thanks, Georgiy

Accepted Solutions (0)

Answers (1)

Answers (1)

sarah_moes
Product and Topic Expert
Product and Topic Expert

Hi Georgiy,

In the vehicle resource master, you can maintain both a mass and volume capacity, plus other units like pallets, etc. If you maintain the volume capacity, it will be respected as long as your product masters also have correct volume data.