on ‎2020 Apr 02 10:29 AM
SAP SAPAPO/BOP Job coming into Check level ( Completing Filter and preparation ) stopping Check status and not moving further. It suddenly stopped at that level from April 1st onwords. We have cancelled for 1st april and 2nd april job also in same status.
Please suggest us what will be the action here and where to verify to process the job to complete.
Request clarification before answering.
Hello,
Look like system does not like April month 😉
Please check the BOP variant if there is any changes to BOP variant or filter.
Stopped at Check status could be due to very high volume as per selection. In that case BOP may take log duration or timed out short dumps.
You may run BOP for one product and check it it works.
Also cross check what all transport moved in Production system in last week.
Check with Basis team for Live cache status and log.
Also when run BOP and it reaches to check status check SM12 locks if any other object locking reach other like time stream parallel order data processing.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 16 | |
| 16 | |
| 5 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.