Hi All,

its regarding the Scope Confirmation and Organisational Structure Phase.

We have completed the scope and Org structure definition and confirmed scope , 

its been 40 Hrs its still showing 90 Percent complete.

Any idea how much time it will take to complete the process in general.

Scope Items Selected - 252 .

Regards,

Asesh Kumar

View Entire Topic
George_Yu1
Product and Topic Expert
Product and Topic Expert

Hi, 

This milestone confirmation step takes about 5.5 hours (see my blog 

From A to Z: Setup a Starter System of the SAP S/4HANA Cloud Public Edition [2024 Edition]).

If longer than that, you need to open a ticket to CBC component asking support to check from the backend. 

Regards,

George