SAP Production Planning

0 Likes
184

Hi,

What setting required that automatically requisition generated for other plant in organisation...

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

You need to setup stock transfer scenario between two plants. You need to extened between both these plants.

You need to have Purchase info record or I would say transportation lane between these two plants.

After that during the Heuristic run system will create stock transfer requisition between two plants

Best Regards,

R.Brahmankar