on 2017 Sep 07 2:28 AM
Hi ,
Heuristics - SAP_MULT_SCH , resulting in error - "Heuristics executed without result".
The clarification needed is , does this work for "Alternate resources" , or only " Alternate modes of the same resources".
Based on Wiki - https://wiki.scn.sap.com/wiki/display/SCM/Scenario+-+Run+Heuristic+SAP_MULT_SCH+in+PPDS+Planning+Boa... ,
It should work on alternate resources , ReS A is overloaded on the particular date , but Res B is not chosen automatically by the Heuristics.
Priority - maintained in the PDS for both the resources - accordingly ,
Help on this is appreciated. Thanks
Karthi