SAP IBP Supply Optimizer: Double Transport Receipts due to late delivery

dominik_karge
Discoverer
0 Likes
735

We are working in weekly buckets and whenever the supply can not happen within current week it is creating additional transport receipts on products where lead time is >0

In fact we are working with confirmed transport receipts (open purchase orders in ECC). As explained whenever the supply can not happen in the current week we are creating additional receipts (which we interface daily as a PR to ECC).

Is there a recommendation how to deal with this using confirmed transport receipts? Right now we are using coupling logic.

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

carsten_schumm
Product and Topic Expert
Product and Topic Expert
0 Likes

Hello Dominik,

I don't get the exact issue. Planning horizon starts in w+0? I.e. the optimizer has planned the transport w+0 => w+1? Is there any adjusted transport involved?

If the 100 confirmed transport receipts should reflect the previously planned transport from the past, you may have to delete the old transport contents (e.g. via initialize lead time horizon parameters).

Kind regards, Carsten