on ‎2019 May 09 5:58 AM
Hello,
We have two different Planning areas P1 and P2 connected to two different supplying S4 system with two Integration profiles. Both of the above Planning areas are Operative planning area.
Issue: In any of the app like View gating Factor/ View Projected stock we can only see always P1 planning area as default and I am not able to find option to switch to other operative PA ie P2 view-projected-stock-app.jpg in these Apps.
Can you please help where I can find these setting or Is there any global configuration for this.
Please see Screen shot below.
Thanks,
Akhilesh
Request clarification before answering.
Hi,
to switch to other PA ie P2 you will have to go via Manage Versions and Scenarios.
Please open this App on the Launchpad, select the PA2 and click on Open In -> View Projected Stock.
Thanks & regards
Michael
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Akhilesh,
Can you remove the default planning area from global parameters then check? It would be under the group HOME_PAGE parameter DEFAULT_PLAN_AREA would be assigned your PA as SAP7. Also check via the Default PA from user icon then "App settings".
Kind Regards,
Veera.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 18 | |
| 15 | |
| 7 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.