on 2023 Dec 14 3:45 PM
Hello IBP experts.
Is there a way to account for a production yield scrap on finished goods production in the time series heuristic?
For example, if production yield is 5% and consensus demand is 100, I want the heuristic to plan at least 105 for production receipts because the yield demand is 5% of what is needing to be produced.
Thank you,
Request clarification before answering.
There is no straight forward provision to mention scrap for FG. However scrap percentage can be specified in custom attribute & demand can be inflated using this attribute.