Hi,

I have my time periods shown as such:

However, it would be ideal for me to have just above the weeks shown, the month they belong to, like this:

Would that be possible to do? If so, how?

Thank you!

Accepted Solutions (1)

Accepted Solutions (1)

piyush_parekh
Active Contributor
0 Kudos

Hi Eva,

Currently this feature is not available in IBP.

Consider changing time period description to incorporate Month to help planners understand which month that TW belongs to.

Regards,

Piyush