SAP EWM: Staging for production - /SCWM/STAGE - Schedule Staging for Production

sap_enthusiastic
Explorer
0 Likes
368

Hi everyone,

I’m having trouble staging some materials for production in a decentralized EWM setup. I’m creating the production order in SAP ERP. The production order was successfully created in ERP, and staging was also successful there.

In EWM, I can see the corresponding PMR, but I’m unable to perform staging for the raw materials using transaction /SCWM/STAGE – Schedule Staging for Production. There is sufficient stock available for all raw materials. I cannot create warehouse Task.

However, I receive the following warning (not an error):

No staging proposal possible for given selection criteria
All staging proposal quantities are 0; no staging needed

Does anyone know what might be missing or what I might be overlooking?

Thanks in advance for any helpful feedback!

sap_enthusiastic_0-1762786280184.png

sap_enthusiastic_1-1762786340326.png

 

 

Accepted Solutions (0)

Answers (1)

Answers (1)

arne_bialas
Explorer
0 Likes

@sap_enthusiastic 

Please check the following notes those might be helpful:

  • SAP Note 2022603 - Production staging in EWM: "No staging proposal possible for given selection criteria"
  • SAP Note 2100035 - Explanation on staging methods in EWM

Maybe those checks will help you:

1. Verify PMR Generation

In transaction /SCWM/PMR:

Check that your PMR contains components with requirement quantities > 0.

Make sure the “Staging indicator” and “Supply area” are correctly transferred from ERP.

The PMR should have item type PPSC or PPPI (not PPSM), depending on configuration.

If the quantities are zero or “staging indicator” is missing -> staging will be skipped.

2. Confirm Staging Method Configuration

You used staging method 3 (Release Order Parts).

Check in /SCWM/PSASTAGE (Production Supply Area Staging Config):

Warehouse Number / Production Supply Area  matches your input.

Staging Method = 3

Bin Determination and Destination PSA Bin are correctly maintained.

Storage type search sequence for staging exists.

If this config is missing -> EWM finds no destination -> “no staging proposal possible”.

3. Check Component Availability

In /SCWM/MON:

Verify that the materials exist in the same warehouse number, same stock type, and same owner as the PMR.

If HU-managed: confirm HUs are in a pickable bin (not blocked, not GR zone).

If batch-managed: check that batch numbers are identical to those in the PMR.

4. Time Window Parameters

In /SCWM/STAGE, you define a time period for requirement start:

If the PMR requirements fall outside that time window, no quantities are proposed.

Try:

Switch “Test Mode” off.  Leave “Number of Hours” empty or set a larger window (e.g., 9999). Execute again. This ensures the system considers all open requirements.