on 2023 Nov 02 10:28 AM
Hi,
When my repl runs as per max quaintly & min quantity system creating multiple warehouses tasks based on stock availability in different bins for the same product.
for example if a Replen request is for 100 units and we have 2 pallets 50 on Day1 and 100 on day 2 receipt the system will pick the full pallet of 50 and then 50 off the full pallet of 100 which is causing extra work.
The ask is that only 1 tasks is created for the first pallet of 50 and the remaining quantity cancelled down, users do not want to go-ahead with multiple tasks for a single request.
Any badi can work to cancel remaining warehouse tasks?
TIA
V.
Request clarification before answering.
Go to master data - storage type - in bottom of the screen - set Repl Tolerance and % setup. It will repl only 1 WT.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi V,
How about the rounding setup on the WPT?
Thanks,
Shamsul Arfeen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Venkaiah,
Isn't it possible to adjust the quantity to make sure only 1 task is created?
Check if this helps for abort task creation /SCWM/IF_EX_CORE_CR_ABORT
Regards,
Pavan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
5 | |
4 | |
4 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.