SAP Digital Manufactoring: Partial Confirmation possible?

doepat
Participant
0 Kudos
176

Hello,

how can i perform a partial confirmation in SAP DM? We don't see a fieldt like quantity or yield etc...? Anybody?

 

br, Patrick

Accepted Solutions (1)

Accepted Solutions (1)

ManoelCosta
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi, assuming you are talking about Discrete execution in Work Center / Operation Activity PODs, see Handling SFCs with Lot Size > 1 in SAP Digital Manufacturing. Br, Manoel

ManoelCosta
Product and Topic Expert
Product and Topic Expert
0 Kudos
Hi! If my answer was helpful, please consider accepting it as solution.

Answers (1)

Answers (1)

ME_scc
Newcomer
0 Kudos

Hello Patrick,

you have to activate the quantity field in the POD designer on the SFC card. You can then enter the quantity you want to confirm in the POD.

ME_scc_0-1749711929687.png

If I understood you correctly.

BR

Marcus