on 2020 Aug 12 10:21 AM
Dear Experts,
We are using SAP B1 for our manufacturing unit.
We are following CELL concept for manufacturing means One Cell have 2 CNC Machine & 1 VMC machine fixed for production of 3 Items A, B & C.
If I run cell completely for Part A, I will get 100 Pcs/Day.As same if I run Part B,150 Pcs/Day & same for Part C,250 Pcs/Day.
When i am getting more schedule from my customer how can I calculate capacity and shift based on these criteria.How can I calculate actual possible production quantity for my plan?