on ‎2020 Jan 09 4:18 PM
Hi,
/SAPAPO/CCR - CIF_DELTAREPORT3
Could you please help us with this issue we are facing all the time when changing process orders from CM25 in ECC.
No issue when doing It in tr. COR2 but instead CM25
It seems that came up after our upgrade to EHP8 in ECC and APO EHP4
We have try to locate the error normally in SLG1 but without any luck, it just went through both systems without any further error details and placed in CCR to updated from there.
It`s a big bussines flow for production that should run smoothly and not be updated manually.
Could you share some experience I will be gratefull.
Thanks in advance
Best regards
Claus
Request clarification before answering.
Hello,
What kind of changes are you doing in CM25?
Is there any difference in order or operation quantity in ECC and APO?
Check in R/3 and in APO system if there is any customer exit or BADI implemented like /SAPAPO/CIF_DELTA3
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 18 | |
| 16 | |
| 5 | |
| 3 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.