S4 HANA PDS subcontracting

carlos_perez8
Participant
0 Likes
977

Hi all


What do I need to trasnfer PDS for subcontracting?

I have BOM, production version, inforecord, advanced flag.

In PDS type in Tcode CURTOADV_CREATE, what should be the option to select?

Accepted Solutions (1)

Accepted Solutions (1)

Sasi2005
Contributor
0 Likes

Hi Carlos,

You would need to create the vendor(Business Partner) in APO. Please use the program /SAPAPO/CREATE_LOCATION , to first create these vendors/subcontractors/business partners in APO before creating the PDS.

Regards

Sasi

Answers (1)

Answers (1)

Sasi2005
Contributor
0 Likes

Hi Carlos,

In which version of S4Hana you are in ? If you are in 1709 and have not applied some of the OSS notes, then you have the radio button "Including subcontracting". You need to select this option for modelling subcontracting scenario. In case you are in higher version of 1909, then depending on the subcontracting business scenario you would need to select relevant radio button. There are 5 scenarios which can be modelled, please check and map your business process against the relevant subcontracting scenario. Please use the below help link from modelling subcontracting business scenario perspective https://help.sap.com/viewer/2b37de3188714044ae00efda7583a428/1809.000/en-US/4c4e52b7eb096ad8e1000000...

These are some of the topics which unfortunately do not have straight documentation.

I hope this helps.

Regards

Sasi

carlos_perez8
Participant
0 Likes

Thansk so much

Regarding notes and following steps for subcontraction withour source of supply, I get this error in CURTOADV_CREATE

Business Partner (vendor) 10000089 is not available in Advanced Planning