S/4 PP-DS collaborative procurement - SPPF033 Determination did not deliver any action templates

former_member594817
Discoverer
0 Kudos
1,301

When using subcontracting scheduling agreements in PP-DS the system displays error message SPPF033 Determination did not deliver any action templates when trying to create delivery relevant releases. A release is created despite the error message but issue (transaction /SAPAPO/BWPSCH2) is not possible because no action was created.

Does anybody know the correct set-up under S/4 HANA 1709 and can help with the correct customizing settings for Define Actions for Issuing Scheduling Agreement Releases?

We are trying to set up action for XML Output of SA Release, but are always getting above error message.

capture1.png

capture2.png

capture3.png

I have also tested with action for Smart Forms Print, but are getting the same error message despite printer maintained in the user master

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member594817
Discoverer
0 Kudos

Solved after renaming action profile and action definition to

/SAPAPO/SAR