on ‎2020 Aug 21 5:45 AM
Hi, we would like to use the A&D functionality for subcontracting with project stock in a S/4 1909 System. In general this solution works but we have some issues / comprehension questions. - w/o project stock: the MRP area subcontrator can be used (with or without A&D). Here the third party provision of components works fine - as described inhttps://help.sap.com/viewer/fe39e10a9a864a8f8dc9537704f0fa13/1909.000/en-US/baa9ce5314894208e10000000a174cb4.html - with project stock: the MRP area subcontractor is ignored. In MD04 for the component (plant area) we get a dependent requirement intwoindividual WBS segments (ProjSt and ScPrSt). The MRP run creates a planned order in the WBS segment ProjSt. Even if we convert the planned order in a purchase requisition (knttp = Q) the indicator LBLKZ in the tab "delivery address" can't be set (supplier can be maintained) -> so a third party provision in the subcontracting stock is not possible. The questions regardingsubcontracting with project stockare: - Is it possible to use the MRP area subcontractor here ? If so, what different settings do we have to make in contrast to subcontracting w/o project stock ? - If using MRP area subcontractor is not possible, how can we implement the process "third party provision of components" here ? - Why are there two individual WBS segments in MD04 (plant area) for the component and why does the MRP run creates the requirement coverage element in the ProjSt segment and not in ScPrSt segment ? Many thanks in advance for any advice Best regardsBritta
Request clarification before answering.
Did you get a resolution on this? We are able to do the project stock subcontracting but not direct delivery. The function of LOG_MM_OM_2 seems to be lost in 1809 as well.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
Special stock indicator for Project Stock at SC vendor is "R" and for Sales Order stock at SC Vendor is "F".
Hope this helps.
Hank Schrandt
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Britta,
you cannot use project or sales order stock for putting into the subcontracting stock because in SAP there is only one special stock possible for a material -> https://help.sap.com/viewer/ec6cdb924d4549bebf1adc4b5cf87b19/6.00.31/en-US/f861bd534f22b44ce10000000...
Best
Alex
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 12 | |
| 9 | |
| 8 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.