Hello SAP Experts,

I am a new to GATP functionality. I have one scenario tried to work on it and Standard SAP system doesn't seem to work this way.

Rules based ATP for location Determination is used for order confirmation.

Loc A Mat 1 500 Pcs

Loc B Mat 1 200 Pcs

Rule 1 LocA --> Loc B

Order comes in for Mat 1 at location A for 1000 Pcs and confirmation was given for 700 Pcs out of which 200 Pcs will be sourced from Loc B. I'm trying to confirm remaining 300 at the end of RLT (Replenishment lead time) as per Customer requirement. Please suggest a way to achieve this.

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

In OVZ9 for your availability check group and cheeking rule A check without RLT field should be untick if you want the system to check the replenishment lead time.

In APO check customization of Maintain Check Control - SPRO- IMG- Advanced Planning and Optimization-Global Available-to-Promise (Global ATP)- Product Availability Check- Maintain Check Control = X confirmation at checking horizon.

Also make sure that in product master TRLT horizon is mainatained.

Best Regards,

R.Brahmankar