on 2020 Jul 17 11:32 PM
We transfer the Purchase order data from ECC to APO through CIF Process once in a week. We do this through REMODGEN/REMODAC2 and then REMODINI.Some times , we observe Rimodini jobs runs longer. What is the recommendation to handle the long-running. Is there any risk if we kill the Rimodini job and restart it?
Request clarification before answering.
Hello,
What is requirement to run initial transfer RIMODINI?
As you can run delta report like /SAPAPO/CCR to make purchase order (transcation data) in sync.
CFM1/3 (REMODGEN/REMODAC2) you should run as batch job on daily basis.
And if needed you can run RIMODINI as weekly.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 8 | |
| 5 | |
| 3 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.