Hello Experts,
we are using the PP - EWM integration via PMR ( Production Material Request). But if you created/sent a PMR to EWM you can not change the components in ERP CO02.
Error Message: You cannot change certain field values; PMR exists for component ....
Is there possibility to cancel the PMR?
Thanks in advance.
Best regards
Joerg
Request clarification before answering.
Hi,
Could you please let us know what changes you are doing in the production order?
I tried to change the quantites of the components in the production order and clicked on "WM Material staging" button and save the order. It updated the PMR in EWM.
Incase you want to cancel the PMR, you can update the component quantities to 0 and click on "WM Material staging" button and save the order. PMR will be updated with 0. (essentially no further use of the PMR).
Best regards
Janardhan S Musigeri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
5 | |
4 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.