Restrict Approval in PR for Past Delivery Dates

sadiq-qamar
Discoverer
0 Kudos
53

Hi Sapians,

I have a requirement from my client where the system should restrict the approver from approving a Purchase Requisition (PR) if the delivery date is in the past. The approval should only proceed once the delivery date is updated to a future date.

Is there a standard way to achieve this in SAP Public Cloud?

Any insights or recommendations would be appreciated.

Thank You

Accepted Solutions (0)

Answers (1)

Answers (1)

jagoda_drwiega
Explorer
0 Kudos

Hello,

Please find KBA Notes about additional BAdI's that consider creating conditions to restart the approval workflow for PR: 

https://me.sap.com/notes/2846174

https://me.sap.com/notes/2775709/E

https://me.sap.com/notes/2848446

Hope you will find it helpful!

Regards,

Jagoda Drwiega | Senior SAP MM Expert

Email: jagoda.drwiega@vico-finconsulting.vicoland.com

Website: www.vicoland.com/sap