on 2016 Feb 24 3:50 PM
Hi,
We can take resource utilization individually from planning board using evaluations.
But is it possible to see the resource utilization for a set of resources means how the operations are loaded and utilization for a group of resources and to see the highest utilized resource from that.
Thanks,
Prasanth
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
Hi again,
To be more specific, we have operations of orders falling on 4 different resources and the operation duration will be different on these resources based on the products.
At present, we can see the utilization for a single resource individually.
Do we have an option to check the four resources together and find which is mostly loaded resources and having more utilization (depends on timelines).
Thanks,
Prasanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
As I understand here also we see individual resource utilization.
But do we have an option or develop a formula within APO that can calculate the smallest amount of downtime on multiple resources (operation falls in both) and between 2 operations (operation of different products).
Then it would choose the smallest amount of downtime for its capacity calculation.
Thanks,
Prasanth
Hi Prasanth,
You can load multiple resources in DS planning board and check for the operations in the planning board and compare them.
For more information on DS planning board you can go through the following link.
Detailed Scheduling Planning Board - Detailed Scheduling Topics - SAP Library
Hope this helps.
Regards,
Jyoti
| User | Count |
|---|---|
| 6 | |
| 5 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.