Relationship between Activities can be broken if we move any operation?

arsenal123
Explorer
0 Kudos
197

Hi Team,

If we are trying to move Granulation Operation, sometimes relationship maintained between Granulation and Tableting is breaking. Granulation and tableting has an

End Start relationship with Max time interval being set as 10,800 sec (3hr) but dragging granulation operation leads to long gap between Granulation and tableting. Similarly it also leads to gap between Tableting and Coating although only 3600 sec( 1hr ) interval has been set between them. Is it normal behavior due to the capacity situation in the resources?

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi Sumanta,

Please check what you have in the "Actions in case of scheduling error" field in the DS strategy profile configuration. If the config allows, the time relationship between activities can be violated by the system during scheduling.