on ‎2016 Nov 04 2:35 PM
While setting non working day under time capacity for a resource , we are receiving an error "Selected unit is not suitable for dimension of resource". This is happening after a recent upgrade.The unit capacity is maintained as 'H'.
Request clarification before answering.
Hi Satyabrata,
Please, make sure attached note below is implemented:
1962164 - Missing days in time stream / Capacity profile / Dump CONVT_OVERFLOW
Afterwards, regenerate the capacity profile and make sure that the first entry / day is not a non-working time.
Regards,
Tiago