on ‎2019 Aug 13 9:30 AM
Hi Experts,
When i try to confirm a operation for production order, system throws error message "Enter Storage Location".
Please help ASAP.
Regards,
Tamil
Request clarification before answering.
Hi Tamil,
If you maintain, in CSO2, it will work only for that BOM of the Header Material.
If you want this storage location should work for all the cases, you should maintain in the Material Master, of that Component in MRP 2 view).
Hope, this is clear. Kindly check & revert back with feedback. If the issue resolved, close the thread by rewarding the Points.
Thanks & Regards : Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Please check the storage location maintain in production order good receipt tab also check for components too.
If issue is for particular product then check storage location maintain in material master MRP2 view.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Enter the Storage Loc from where you want to consume the stock, while backflush.
click "Goods Movement" option in the confirmation screen, you will find your components, then enter the right Storage loc.
Best Regards,
Kumar semmalai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 6 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.