cancel
Showing results for 
Search instead for 
Did you mean: 

Question on deallocated orders in PPDS

Former Member
0 Kudos
1,248

Dear All,

We have a situation where after sequencing the orders based on date and time some of the orders are getting deallocated at the end of period and in some cased the orders are getting De-allocated at the beginning of period.

Now my question is that in which situation or condition the De-allocated orders are taking place at the beginning and End of the period ?

I would appreciate if somebody can explain the complete process of De-allocation including above scenario .

Many thanks

Best Regards

Deba

Accepted Solutions (0)

Answers (2)

Answers (2)

tiago_furlanetto
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Debasis,

If in the strategy settings of the heuristic the "Action in Case of Scheduling Error" is Deallocate, the activities which could not be scheduled may be deallocated.

Regards,
Tiago

Former Member
0 Kudos

Hi Tiago,

Thanks for your reply.

We are running scheduling heuristic interactively in dashboard with the following setting :

Scheduling Mode : Find slot

Planning Direction: Forward

The Action in case of Scheduling error : "Sched. Infinitely and if Necessary Break Pegging Relationship."

We are trying to sequence the orders week by week. The issue is that system put the De-allocated orders at the beginning of the period in some case and in some cases the De-allocated orders are taking place at the end of period and we do not know why the system is behaving in this way.

Please let me know if you need any more details.

Best Regards

Deba

Abhishek_Kunchala
Active Participant
0 Kudos

Debasis,

Can you tell us which scheduling heuristic are you using? For Ex, De-allocation of operations can occur when there is a firmed operation in an order and the scheduling heuristic tries to reschedule the remaining operations but it cannot move them due to some relationships between these operations. In situations like this, deallocation occurs.

Regards

AK

Former Member
0 Kudos

Hi Abhishek,

Thanks for your reply.

We are running scheduling heuristic interactively in dashboard with the following setting :

Scheduling Mode : Find slot

Planning Direction: Forward

Action in case of Scheduling error : "Sched. Infinitely and if Necessary Break Pegging Relationship."

We are trying to sequence the orders week by week. The issue is that system put the De-allocated orders at the beginning of the period in some case and in some cases the De-allocated orders are taking place at the end of period and we do not know why the system is behaving in this way.

Best Regards

Deba

Abhishek_Kunchala
Active Participant
0 Kudos

Debasis,

What are the strategy parameters for dependent objects in the heuristics? Are you considering time relationships?

Regards

AK

Former Member
0 Kudos

Hi Abhishek,

Yes we are considering time relationship in strategy parameters for dependent objects.

Please find attached screenshot for more details on strategy parameters for dependent objects.

Best Regards

Deba