Hi All,

Is it possible to make CTM obey the factory calendar. I understand that we can define a CTM time stream and assign it to the CTM profile. However this time stream doesn't have reference to the factory calendar unlike normal planning calendar in APO.

How can we make CTM obey factory calendar.

Best Regards

lss

Accepted Solutions (1)

Accepted Solutions (1)

RahulHanda
Active Contributor
0 Kudos

Hi

If you are talking about factory I am assuming you have production facility hence resources in the same. In resources you assign calendar. The availability of this resource depends upon this factory calendar so yes CTM can obey factory calendar.

If your scenario is different then mention the same.

Regards

Rahul

Answers (1)

Answers (1)

Former Member
0 Kudos

Lss,

It is unlikely that you would even want for CTM to 'obey' a single factory calendar.  In most implementations, there are many factory calendars that must be accommodated.

As mentioned by expert Rahul, the typical solution involves assigning the appropriate Factory Calendars to the resources.  These factory calendars will then be used by the CTM engine during planning.

Best Regards,