on 2015 Jul 28 7:07 AM
We are implementing supply planning and we have 9 manufacturing plants and 20 DCs (There is NO multi-sourcing and 1 product is produced only at one plant). We are running Heuristics which provides us unconstrained supply plan, and then we use adjusted production key figures to make the supply plan feasible and balance the resource capacity load.
Now we have some questions to support this process.
Thanks
Girish
Request clarification before answering.
Hi Girish,
I think question 1 and 3 can be resolved by using planning units. If you want a planner to restrict planning only for certain plants, you can assign associated planning units to their role.
For question 2, re-planning can be done for all the plants irrespective of where adjustment have been made and where not. The system will consider adjusted values and will generate new receipts while for the plants where no adjustment has been made, the earlier plan will remain as it is.
The requirement mentioned in question 4 can be achieved by using parameter RESET_ADJUSTED_KEY_FIGURES with parameter value YES.
Thanks,
Rohit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Rohit, your information is very useful. One more questions here with deleting old receipts (regular output KFs like transport receipt, production receipts etc).
So once months rolls forward, how to delete the receipt /Supply key figures (System generated ones) that goes in the past (For example anything in July will go in past once August Starts). as once we replan in august it will only replan August onwards.
Thanks
Girish
Hi Aditya,
Two points here
- We are not measuring any Production receipt Vs Actual in SOP HANA
- If we have any receipts in past, it may create wrong calculation for projected inventory KF
We basically wanted to have all the calculation should happen from present bucket and should not count any thing which may appear in the past.
Thanks
Girish
Hi Rohit,
It is not deleted automatically when the month rolls forward, even if we take the fresh supply planning run it replans from curent bucket onwards and don't touch anything in the past.(Demand in the past exists or doesn't exist it doesn't matter as old receipt exists as it is after taking supply planning run)
There is a parameter suggested by Pramod, will try if this helps in this case.(INITIALIZE_LEADTIME_HORIZON<> YES”)
Thanks
Girish
| User | Count |
|---|---|
| 12 | |
| 9 | |
| 8 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.