on 2024 Oct 14 9:43 AM
Hi
We currently have a scenario whereby for material A:
Alternative Uom are set as follows:
The issue units in Work scheduling is set to ML and WM issue unit is also set to ML.
The Demand created from PIR conversion is correct, the coverts the required 10ML from a BOM to 0,2EA which is correct. however for a demand from a SO, the system does not covert the required 10ML to 0,2EA, instead it round it up to 1EA.
Request clarification before answering.